Name of Project |
: |
Construction of four (4) Orepasses |
Project Duration |
: |
About four (4) and half years, from 1994-1997 |
Resources |
: |
There were about eighty (80) expatriates ex-South Africa |
Project Location |
: |
PTFI’s Underground |
Liaison Points |
: |
Jakarta |
Method |
: |
Raiseboring Technology |
Machine |
: |
HG 330 |
Diameter |
: |
up to 4.14 meter |
Length |
: |
up 630 meter / orepass; for a total length of over 2500 meters |
Mobilization & Demobilization |
: |
It required fourty (40) 20 ft. Containers plus two (2) 40 ft. containers to mob and de-mob the rig with all the accessories
|
Route |
: |
South Africa, Singapore, Amamapare, Highland, Job Site |
Reward |
: |
Best Underground Jobsite |
Year |
: |
1994 |
Special Note |
: |
The project was executed in three shift 24 hours and seven days a week schedule
|